Project Overview

Dortek reached a point where their existing infrastructure was limiting production. Their paint booths used standard double doors that were too small for their larger products, creating a bottleneck that slowed down their entire finishing process.

Our Solution

We overhauled the booths by removing the old doors and installing two insulated industrial roller doors. This project involved:

  • Expanding the access points from 2 metres by 2 metres to a much larger 4 metres by 3 metres on both booths.
  • Improving thermal efficiency with insulated door lath.
  • Enhancing production capacity by allowing for the painting of oversized items.
The Result

By doubling the entry space, the client is now able to take on larger contracts and process their products much faster than before, significantly increasing their daily output.